PSE&G PAVEMENT RESTORATION PROJECT

Road work (2)

Dear Residents,

Many of you were part of PSE&G utility upgrades last year. PSE&G has now contracted TILCON to repair the roads which will consist of milling and paving.  I have been notified that the work is scheduled to begin today.  This work is weather-related, and rain may cause a delay in completion of work.  Below is the current schedule for PSE&G’s asphalt restoration project.  All questions and concerns may be directed to PSE&G using the phone number on the door hanger you received last week.


MILLING

  • JUNE 4, 2018             Prospect Pl. & South St.
  • JUNE 5, 2018             Canfield Rd., West Dr., & Crescent Dr.
  • JUNE 6, 2018             Crescent Dr., Bradley Rd., & Parker Rd.
  • JUNE 7, 2018             Washington Ave., & the intersection @ Normandy Pkwy/  Plymouth Rd., Godet Pl., & Olmstead Rd.

PAVING

  • JUNE 11, 2018           Prospect Pl., South St., Bradley Rd. & Parker Rd.
  • JUNE 12, 2018           Crescent Dr., West Dr. & Canfield Rd.
  • JUNE 13, 2018           Washington Ave., & the intersection @ Normandy Pkwy./ Plymouth Rd., Godet Pl., & Olmstead Rd.

Sincerely,

Thomas J. Eschmann

Superintendent